⭐ Work was running 47 weeks behind, mainly because of unexpected…

Monday, January 23, 1961 All day

By 23 January 1961, work was running 47 weeks behind, mainly because of unexpected difficulties (inclement weather, unexpected difficulty diverting stormwater, construction beginning before proper construction drawings had been prepared, changes of original contract documents) Wiki link